Step 6 - Mounting Blending
Now you the box is nearly finished. You just have to mount the blending to cover the components. Optional you can mount handles to carry the box.
Add back blending
(Better do it before interface blending because the inteface blending is not flat.)
- Put SolarBox on the interface.
- Position square nuts. They must have the same position as the holes of the blending.
- Put blending on the frame.
- Insert bolts through the blending into the square nuts. Tighten the bolts.
Mount side blending
- Put the SolarBox on the side.
- Position the squre nuts.
- Put the blending on the frame.
- Insert bolts through the blending into the square nuts. Tighten the bolts.
Mount to blending with handles.
- Put the SolarBox on the bottom.
- Position squre nuts for the top blending.
- Put top blending.
- Put handles on the top blending.
- Insert longer bolts through the handles, the blending and squre nuts. Use normal bolts for other parts of the blending.
- Tighten the blending.
Mount last side blending
- Check once more if all the connection are good.
- Insert the fuse.
- Put the SolarBox on the side.
- Position the square nuts.
- Add the blending.
- Tighten the bolts.